2020 Bond Project Overview
2020 Bond Project Overview
2020 Bond Program Summary
The 1.2 billion-dollar 2020 School Bond allows PPS to continue the vital work of improving our aging school buildings in several key areas as well as upgrading important educational infrastructure issues. Thank you voters!
- 2020 Health and Safety Projects - new roofs and mechanical systems, seismic retrofits, plus accessibility and security upgrades - $217.6 Million.
- 2020 Modernizations - transforming the historic Jefferson and Benson Polytechnic High Schools into modernized 21st century centers of learning. Plus, the construction of a new Multiple Pathways the Graduation Building on the Benson campus - $527 Million.
- New curriculum materials and textbooks - $53.4 Million.
- Educational technology upgrades to support classroom and distance learning, plus updating classroom and district technology devices. - $128.2 Million.
- Planning the future modernizations of Cleveland and Ida B. Wells (formerly Wilson) High Schools - $42 Million.
- Development work on The Center for Black Student Excellence - $60 Million.
- Upgrading PPS Special Education Learning Environments (SPED) - $13.4 Million.
2020 Bond Program Budget Table
| Modernizations | |
| 2017 Bond Balance | $152,000,000 |
| MPG Building | $64,000,000 |
| Jefferson High School | $311,000,000 |
| Center for Black Student Excellence | $60,000,000 |
| Cleveland -Planning & Design | $20,000,000 |
| Wilson -Planning & Design | $20,000,000 |
| Roosevelt -Planning & Design | $2,000,000 |
| Capacity | $10,000,000 |
| Educational Improvements | |
| Technology | $128,200,000 |
| Curriculum | $53,444,000 |
| SPED Learning Environments | $13,400,000 |
| Physical Facility Improvements | |
| Roof | $65,700,000 |
| Mechanical | $75,000,000 |
| Security | $25,900,000 |
| Seismic | $17,200,000 |
| ADA | $33,800,000 |
| Contingency & Administration | |
| Administration | $63,098,640 |
| Contingency | $93,275,360 |
| Total | $1,208,000,000 |
Click here to view the 2020 Bond Program Budget Table
|Español |Tiếng Việt | Русский | Soomaali | 中文
2020 Bond Program Conceptual Schedule
Click here to view the conceptual schedule.