Modernization projects at Lincoln, Madison and Kellogg are taking shape
2/10/2020Work is continuing on three major modernization projects made possible by Portland voters passing the 2017 Health, Safety and Modernization Bond. The rebuild of Lincoln and Madison high schools, and the construction of a new Kellogg Middle School, are at different stages; here is an update.
Stadium work and recycled concrete at Lincoln
The Lincoln High School Rebuild project is now underway and big changes are already visible on site. Over the holiday break, the Hoffman Pacificmark team set up construction fencing and began work demolishing the football stadium’s old grandstand and press box. The turf field was also removed.
The site is now being leveled using trucks and heavy equipment. Hoffman Pacificmark used over 13 million pounds of recycled concrete saved from a local project site for the base rock level. This recycling effort keeps a significant amount of material out of local landfills and saves money that can be used elsewhere. Foundation work for the new six-story Lincoln High School will begin shortly.
See the latest Lincoln project photos
Interior modeling and seismic retrofit underway at Madison
Work is progressing at Madison High School, with interior structural remodeling and seismic strengthening underway. In the new gym building, construction masonry unit (CMU) blocks are being installed as the weight room, wrestling room, and locker rooms begin to take shape in the lower gym level.
In the administration and science classroom wing, the concrete slab has been poured and structural steel started getting put in place. In the fine arts building, the orchestra pit CMU blocks continue to rise as the black box theater footings are being installed.
See the lasted Madison project photos
Watch a time-lapse video of the Madison work:
The framework for the new Kellogg nearly complete
Steel framing on the new Kellogg Middle School is almost complete, with the final steel beam to be placed atop the three-story learning suites structure by the end of February. Learning suites are groups of classrooms connected together on each floor in an extended learning area to promote collaboration. The gym and performing arts structures, whose concrete tilt panel walls were raised up in November, will soon be sealed off from the outside elements, allowing interior wall framing to begin. At that point, mechanical, electrical and plumbing systems can start to be installed within the building.
Planning for furnishings, fixtures, equipment and classroom technology is underway to prepare the building for new administrative staff to occupy the completed building in the spring of 2021. This will allow them to set up the new Kellogg Middle School program in the building ahead of the arrival of students in the fall of 2021.
See the latest Kellogg project photos
To see the latest images of the work and to get Bond project updates visit the Bond Program Webpage.
-David Mayne, Bond Communications Manager
By Month
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- June 2023
- May 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- June 2015