A busy summer of bond work in PPS
9/9/2019This past Saturday a ribbon-cutting ceremony celebrated the opening of the newly modernized Grant High School. Grant was completed after a two-year construction period and is the last project from the landmark 2012 School Improvement Bond.
The 2012 Bond funded the modernization of three aging high schools, Franklin, built in 1915, Roosevelt, in 1921, and Grant in 1925, along with the rebuilding of a brand-new Faubion PK-8. The 2012 Bond also brought improvements to 51 other schools across the district including new roofs, seismic upgrades, accessibility projects including new elevators and upgrades to middle school science classrooms.
The success of the 2012 Bond paved the way for the May 2017 Bond that continues the District’s commitment to rebuilding all of our schools over the next 30 years. A look at some of the work that went on during a busy summer of bond and construction work in 2019:
Madison demolition and Kellogg construction
Construction began on a modernized Madison High School. Hazardous materials abatement took up much of the summer with demolition beginning in August.Just over a week ago, the foundation was poured at the new Kellogg Middle School, a planned state-of-the-art campus in Southeast Portland. Both Kellogg and the new Madison will open for the 2021-22 school year.
Health and safety work continues across the district
Health and safety upgrades that have touched every school across the district continued this summer with improvements in water quality, the remediation of radon, lead paint and asbestos. District-wide security upgrades also got underway this August.Although the May 2017 bond criteria provided funding and scope for only 11 schools, the security program team recognized the need for additional security across the district and is now providing security improvements at 88 schools and facilities. The work is expected be completed across the entire district during the 2019-20 school year.
New roofs at Sitton, Rigler and Jackson
Sitton Elementary, Rigler Elementary and Jackson Middle School received new seismically strengthened roofs. Because of its size, the Jackson project is scheduled over two years. It will start up again in June 2020 and be completed by the start of school in August of 2020.Seismic retrofit underway at Hayhurst Elementary
Hayhurst Elementary received the first half of a full seismic retrofit that will bring the school up to immediate occupancy seismic standards. Like Jackson, the remaining work will resume next summer and be completed by the fall of 2020. PPS was able to leverage existing bond funds together with grants from our state partner, Business Oregon, which operates the Seismic Rehabilitation Grant Program (SRGP), to undertake the Hayhurst project. SRGP funds have made seismic retrofit projects at Alameda, Franklin, Lewis and Grant possible over the last seven years.Water quality improvements continue with pilot program
PPS is also leading the way in water quality with a new pilot program that could lower lead levels in our school’s water to among the lowest in the country while saving millions of dollars in construction costs.The PPS Water Quality Program successfully replaced all the common area drinking water fixtures in the District last year. However, several schools still have a large number of drinking fixtures that test high for lead due to suspected problems with the pipes in the walls. These fixtures have remained off since 2016 and now require expensive and disruptive in-the-wall partial pipe replacement.
Six schools -- Arleta, Duniway, Jefferson High School, Llewellyn, Rigler and Robert Gray Middle School -- are getting new Drinking Water Stations (DWS) fitted with a highly effective 3M lead filter as part of a PPS pilot program. This program is something no other school district in Oregon is doing and a significantly less expensive alternative to replacing pipes in the walls.
The initial results are very promising, with many fixtures showing levels at less than 1 part per billion (ppb). State-mandated action levels for lead are 15 ppb. Frequent monitoring of the water at these schools over the next several months will determine if the program can be rolled out to additional schools. For more information, visit the PPS Water Quality Pilot Project web page.
-David Mayne, Bond Communications Manager
By Month
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- June 2023
- May 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- June 2015