2020 Bond Project Overview

  • 2020 Bond Program Summary
    The 1.2 billion-dollar 2020 School Bond allows PPS to continue the vital work of improving our aging school buildings in several key areas as well as upgrading important educational infrastructure issues. Thank you voters!

    • 2020 Health and Safety Projects - new roofs and mechanical systems, seismic retrofits, plus accessibility and security upgrades - $217.6 Million.
    • 2020 Modernizations - transforming the historic Jefferson and Benson Polytechnic High Schools into modernized 21st century centers of learning.  Plus, the construction of a new Multiple Pathways the Graduation Building on the Benson campus - $527 Million.
    • New curriculum materials and textbooks - $53.4 Million.
    • Educational technology upgrades to support classroom and distance learning, plus updating classroom and district technology devices. - $128.2 Million.
    • Planning the future modernizations of Cleveland and Ida B. Wells (formerly Wilson) High Schools - $42 Million.
    • Development work on The Center for Black Student Excellence - $60 Million.
    • Upgrading PPS Special Education Learning Environments (SPED) - $13.4 Million.

     2020 Bond Program Budget Table

    Modernizations
    2017 Bond Balance $152,000,000
    MPG Building $64,000,000
    Jefferson High School $311,000,000
    Center for Black Student Excellence $60,000,000
    Cleveland -Planning & Design $20,000,000
    Wilson -Planning & Design $20,000,000
    Roosevelt -Planning & Design $2,000,000
    Capacity  $10,000,000
    Educational Improvements
     Technology $128,200,000 
     Curriculum $53,444,000 
     SPED Learning Environments $13,400,000 
    Physical Facility Improvements
     Roof $65,700,000
     Mechanical  $75,000,000
    Security $25,900,000
    Seismic $17,200,000
    ADA $33,800,000
    Contingency & Administration
     Administration  $63,098,640
     Contingency $93,275,360
    Total $1,208,000,000

    Click here to view the 2020 Bond Program Budget Table
    |Español |Tiếng Việt | Русский | Soomaali | 中文

    2020 Bond Program Conceptual Schedule
    2020 Bond Schedule icon
    Click here to view the conceptual schedule.