  •  Seismic Strengthening banner

Improving the seismic safety of PPS buildings is an important component of the School Building Improvement Bond program and a priority for the District.  The majority of PPS schools were built before WWII at a time when knowledge and concerns about seismic safety were very different from what we know today.

The 8-year School Building Improvement Bond approved in November 2012 seeks in part to address the seismic safety issues found in many of our schools.  The Bond will seismically strengthen schools through roof replacements, seismic rehabilitation, modernizations and incremental seismic improvement projects. 
 
The modernized or rebuilt schools, Franklin H.S., Faubion PK-8, Grant H.S. and Roosevelt H.S. will be brought up to current seismic code.

Seismic Projects


Project Selection Criteria

The 2012 Expected Seismic Performance (EPR) Ratings were used in the development and prioritization of schools for the 2012 bond. These classified Portland Public School facilities, by campus, into general groupings to describe their expected performance in an earthquake, using Good, Fair, and Poor. All Poor EPR schools in operation during bond planning have or will receive incremental seismic improvements. For more information visit the Facilities and Asset Management Seismic page.
 

Schools receiving seismic strengthening
Projects in blue are complete as of the summer of 2016.  Click on them to view the project website
Abernethy K-5
Alameda K-5 Arleta K-8 Beach PK-8 • Beaumont MS • Benson HS • Beverly Cleary K-8 • Creston K-8 • Duniway K-5 • Grout K-8  • Hosford MS • Jackson MS • James John K-5Jefferson HS Lane MSLlewellyn K-5MLC K-12Woodlawn PK-8 

Schools receiving roof replacement/seismic bracing
Abernethy K-5  Ainsworth K-5Alameda K-5Arleta K-8 • Beverly Cleary K-8 • Boise Eliot PK-8Bridlemile K-5 • Buckman K-5 Chief Joseph K-5 Cleveland HSCreative Science K-8Creston K-8 Hayhurst K-5Hosford MS • Jackson MS • James John K-5Laurelhurst K-8Maplewood K-5Meriwether Lewis K-5Sabin PK-8Sellwood M.S. Stephenson K-5Wilson H.S.

Projects using state SRGP funds for seismic work

The Franklin High Modernization was awarded a $1.3 million dollar grant for seismic rehabilitation. Learn more here
 
Alameda K-5 School was seismically upgraded in summer 2013 using Bond funds and a $1.5 million Seismic Rehabilitation Grant Program award from the State of Oregon, administered through the Office of Emergency Management. View the Alameda bond work poster.
 
 

Stay Informed


IP/ Summer incremental seismic strengthening work 
 
Summer bond work includes incremental seismic strengthening.  Typically, this work is one step of a phased approach to a complete retrofit to meet ASCE/SEI 41-13 Basic Performance Objective for Existing Buildings for Risk Category III buildings. The seismic roof strengthening during roof replacements, chimney and parapet bracing and hollow clay tile partition bracing along major routes of egress meet Damage Control for BSE-1E and Limited Safety for BSE-2E. Additional strengthening work will be required in the future to have structural performance complying with the ASCE/SEI 41-13 BPOE.

PPS Incremental seismic strengthening work includes:
  • Roof diaphragms
  • Strengthening wall to roof connections
  • Bracing parapets
  • Shear wall strengthening
  • Bracing unreinforced masonry
  • Reducing chimney height

PPS Modernizations
 
The seismic renovation for Franklin, Roosevelt and Grant high schools will be designed to meet ASCE/SEI 41-13 “Seismic Evaluation and Retrofit of Existing Buildings.”  ASCE/SEI 41-13 is a national standard published by the American Society of Civil Engineers / Structural Engineers Institute and is recognized by the state of Oregon as an acceptable code for seismic renovations and is considered state of the art. 
 
While the ASCE/SEI 41-13 performance level is often referred to as ‘Life Safety’, it actually consists of two performance levels, a slightly higher level for less intense earthquakes and slightly lower level for more intense earthquakes.  The Basic Performance Objective for Existing Buildings (BPOE) used for these buildings includes two structural performance levels, Damage Control at the BSE-1E seismic hazard and  Limited Safety structural performance at the BSE-2E seismic hazard.
 
The intent of ASCE/SEI 41-13 design is to prioritize protection of the occupants, not the buildings.