• The May 2017 Bond provides $12 million for asbestos remediation.

    This is a list of asbestos remediation projects for 2018 and 2019.  Many more schools will receive asbestos remediation work in the coming years through the May 2017 Health Safety and Modernization Bond.

    2019 Asbestos Remediation Projects

    Beaumont Middle School
    Asbestos removal and re-insulation of severely damaged piping insulation from basement and portable classroom crawlspaces.  Removal of approximately 15,000 square feet of accessible asbestos containing floor tile & mastic from basement, first and second floors and replacement with new non-asbestos flooring.

    Capitol Hill
    Abatement of floor materials. New flooring installed. 

    Jackson Middle School
    Asbestos removal and re-insulation of severe to moderately damaged asbestos fireproofing from structural steel decking from; C-Wing basement tunnel entry, Auditorium attic mechanical spaces, D-Wing 1st floor above Library ceiling, and B-Wing above Cafeteria ceiling.

    Lane Middle School
    Abatement of floor materials & pipe insulation in various locations (Tunnel and Crawl Space Included.) New flooring installed. 

    Marysville K-8
    Asbestos removal in the crawl space.

    Rigler Elelmentary
    Abatement of floor materials & pipe insulation in various locations (Tunnel and Crawl Space Included.) New flooring installed.

    Vestal K-8
    Abatement of floor materials & pipe insulation in various locations (Tunnel and Crawl Space Included.) New flooring installed.

    2018 Asbestos Remediation Projects

    Tubman Middle School
    Removal and of asbestos piping insulation from first and second floors (Above Ceilings).  Complete removal of all boiler and piping insulation from the boiler room and selective ceiling removal and replacement throughout building.  Removal and replacement of all accessible asbestos containing flooring from first and second floors and the replacement with new non-asbestos flooing.

    Chapman Elementary School
    Removal of approximately 20,000 square feet of accessible asbestos containing floor tile & mastic from basement, first, and second floors and replacement with new non-asbestos flooring.

    Jefferson High School
    Removal of approximately 50,000 square feet of accessible asbestos containing floor tile & mastic from basement, first, second, and third floors and replacement with new non-asbestos flooring.