-
Harriet Tubman Middle School environmental background (prepared for Faubion K-8 move-in)
11/6/2017The following information has been reviewed to date and provides insight into the due diligence and work that was performed at Harriet Tubman Middle School to prepare the building to receive Faubion K-8 students, as well as maintenance and safety testing work completed during the two years that Faubion was housed at the facility. We have also included information on safety assessments that will take place as part of the effort to prepare the building to open as Harriet Tubman Middle School.
Prior to Faubion occupying Tubman:
- The Office of School Modernization oversaw approximately $1.1 million dollars in preparatory work prior to the Faubion use of the Tubman campus. This work included asbestos abatement, balancing of air handling units, deep cleaning, etc.
See Attachment No. 1a, No. 1b - A DEQ Fact Sheet entitled “Air Toxics Monitoring at Harriet Tubman Leadership Academy in Portland”, references and summarizes EPA monitoring from 2009 and 2011 at the school. This fact sheet describes the discovery of cadmium in the air and the subsequent tracing to the glass manufacturers which no longer exist. Other air toxics measured were noted as “…below EPA’s level of concern…”.
See Attachment No. 2
During Faubion occupying Tubman:
- A February 2016 test ordered by PPS and conducted by PBS Engineering and Environmental for cadmium and arsenic in the air and soil, stated “There were no detectable levels of either cadmium or arsenic reported for any of the air and soil samples”.
See Attachment No. 3 - An independent OHA report on soils was published in March 2016 and concludes “…that exposure to levels of metals in soils around Uroboros Glass are too low to harm the health of people in the surrounding community…”.
See Attachment No. 4 - The Harriet Tubman building had a series of roof leaks from rain water in the past two years which seriously inconvenienced the staff. Most leaks occurred repeatedly in the main office area and library. Multiple efforts to patch the roof were not successful. Post- repair mold testing indicated no mold growth in the room tested (105). Upon observation last week, room 105 has leaked again and several library skylights are boarded up.
See Attachment No. 5a, No. 5b - Some of Faubion Principal Jennifer McCalley’s concerns, such as roof leaks, rodent problems, transients, and direction to not have heavy traffic around the back/above the slope to the freeway, are validated by the Risk Management Department’s review of work orders, injury reports, First Response dispatch records, PPB case number listing, sharps container servicing, discussions, etc.
See Attachment No. 6a, No. 6b, No. 6c, No. 6d - A complete asbestos inventory is on file with the Risk Management Department. Initial short-term radon testing was completed in 2016, no radon levels met an action level, no further action is required for 10 years.
See Attachment No. 7a, No. 7b
Next steps: air quality and soil stability
- Background: A geotechnical preliminary analysis was conducted in 2014. The preliminary analysis document was based on a site walk and review of available historical information about the property. This document includes a review of current conditions/ existing data, possible causes for the settlement/lateral movement that is occurring, potential remedial options/estimate budgets, and additional geotechnical studies required to refine the remedial options.
June 2017: The contract proposal defining the scope, schedule and fee for the 2-year geotechnical study is per the recommendations of the preliminary analysis document. This study includes installation of three 50-foot deep inclinometers and 24 survey monitoring points to measure settlement/lateral movement (and water level through the piezometers in the inclinometers) over a 2-year period of time.
Current October 2017: - Inclinometer Initial Reading Update: An initial reading update was requested by the district. The letter provides information about the general subsurface soils and any changes observed in the monitoring instruments between July 9 and September 29, 2017. See Attachment No. 8a, No. 8b, No. 8c - Senior leadership at DEQ has been contacted, and PPS has secured a commitment from the Northwest Regional Administrator to enlist the EPA to partner with PPS in designing and conducting air monitoring related to I-5 emissions, along with analysis of monitoring data. An Action Plan is projected to be complete by December 1, 2017. Once developed, the Action Plan will outline the time table to complete the comprehensive analysis. PPS will conduct this work as expeditiously as possible. PPS also recognizes the need to install a high performing HVAC system throughout the building to improve indoor air quality, as well as perform any deferred maintenance that would be required before students and staff occupy the Harriet Tubman building.
- The Office of School Modernization oversaw approximately $1.1 million dollars in preparatory work prior to the Faubion use of the Tubman campus. This work included asbestos abatement, balancing of air handling units, deep cleaning, etc.
By Month
- March 2025
- February 2025
- January 2025
- October 2024
- September 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023
- August 2023
- June 2023
- May 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- October 2020
- September 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2016
- January 2016
- December 2015
- June 2015