• Construction Updates

    Madison DAG & MPC meeting minutes and presentations have been move to here.

    Oct 2020
    Principal Skyles tours the site

    Principal Adam Skyles tours the site

    Madison Principal Adam Skyles toured the site in late September with Project Manager Jessie Steiger.  On their walk they were able to see the progress the project has made in brick installation on the new Theatre, that drywall and paint is happening and work is progressing in the new commons, the new connecting walkways and both new gyms. Also underway are improvements to the track and field area including concrete wall at the concessions and the continuation of fencing at the backstops.

    exterior of the gym building

    On the exterior of the gym building, waterproofing is up and in the SW corner brick installation has started.  On the interior, work on the locker rooms and the electrical room continues with plumbing the current focus.

     Auxiliary gym interior
    The Auxiliary gym is also coming along.  This view looking west towards the large window at the mezzanine level gives early indication of the great views into and from this space.

    the new commons

    In the center of the campus work is progressing in the new commons with the completion of the radiant slab this month and the connecting walkways beginning to take shape.  In the South Campus Career and Technical Education CTE/ Classroom wing, drywall has been installed and Mechanical/Electrical/Plumbing work is underway.

     CTE Engineering classroom

    In this CTE Engineering classroom, where the drywall has been completed the alcove awaits future 3D printers and other equipment. Career and Technical Education (CTE) includes a wide variety of disciplines that allow students to experience rigorous, hands-on learning and acquire skills that are transferable to a multitude of future career pathways in healthcare, construction, technology, engineering, digital media, and many more.

    new Theater exterior brick work

    Over at the new Theater, scaffolding has been installed throughout the theatre interior to enable the crew to start Mechanical/Electrical/Plumbing rough-in above the Theater seating.  On the exterior of the building, waterproofing and brick installation is well underway.

    Science and Administration wing that overlooks 82nd Ave

    In the Science and Administration wing that overlooks 82nd Ave windows are being installed and exterior waterproofing is underway. The building’s many windows allow for beautiful vistas both inside and out. For students, access to natural light in their classrooms has a proven beneficial impact on learning and well-being.

    Aug/Sept 2020
    Steady progress across the site.

    Madison gym roof Aug 2020.

    Good weather throughout the summer has allowed work to steadily progress throughout the Madison modernization project. The roof to the gym and auxiliary is up now as is the steel staircase connecting the two floors. 

    Madison Framing admin wing Aug 2020

    Framing and insulation is taking place in the adminstration/science and classroom wings in the south side of the site.

    Madison Theater exterior Aug 2020

    The exterior of Theater.

    July/Aug 2020
    Steel work captivates the site.

    Steel framing in new gym

    This month has seen lots of steelwork in the new commons area of Madison. A major focal point of the work is the commons bridge. Plumbing in the all-gender restroom is making good progress and in the north classroom wing, all the electrical, mechanical and drywall is in place. 

    Steel framing in auditorium

    In the new auditorium, theater rigging and catwalks are nearing completion and the stage floor concrete slab was poured -- including trap door openings!  On the back wall, framing for the control booth has started and structural steel is being installed at the theatre lobby. On the south side of the building steel joists are being installed and roof work and waterproofing are ongoing.

     Commons bridge

    On the west side of the campus, interior framing, electrical, plumbing rough-in work and drywall installation on the classrooms is well underway. On the roof, the installation of heating and cooling mechanical equipment and ductwork is also moving ahead at a steady pace.

    Drywall work in a classroom

    At the Crossroads, electrical and plumbing work is proceeding and structural steel is being installed in the computer lab and future Maker Space. In the administration and science wing, the interior plumbing is being roughed-in and sprinkler lines are being installed. Roofing is also underway. In the new gym building, wall installation is nearly complete.

    June 2020
    Summer construction underway.

    Madison Theater interior

    As work at Madison moves into summer, many areas are shaping up. At the front of the school the new Science Wing is taking shape with exterior framing underway. Interior framing also continues in this area as well as in the nearby Administrative Offices. Roofing over the science wing is 60% complete. In the new Commons, the concrete columns are nearly finished and the main wall in the commons has been formed with shotcrete.  Delivery of steel for upcoming framing work has started.  On the north park side of the campus, glass is being installed in the building.

    In the new Arts Wing, the theatre the walls are up and concrete work is complete. Inside, steel work and rigging on the trusses and catwalk are underway and the main stage area is in place. In the Black Box theater, walls are nearing completion. Concrete masonry block walls are also nearly finished in the band and choir classrooms. On the other side of the hallway of the Arts Wing interior framing work is starting in the 3D Arts, 2D Arts and Photography classrooms. Overhead steel frame work is also moving quickly.

    Steel framing at Madison

    In the classroom wing at the southwest side interior overhead electrical, mechanical and plumbing rough-in is being installed as well as steel framing in classrooms. The new gym continues to make great progress. On the ground floor where the locker rooms, training room, team rooms, and storage will reside concrete masonry block work is complete.  This level is also home to wrestling, yoga and dance as well as a new weight room with garage doors that will open onto the path to the field.  Moving up to level 2, concrete masonry block installation is beginning on the new auxiliary and main gym.

    Madison Gym construction

    In the field area demolition of the old stadium is complete with only the old blue paint and small footing remaining. Later in the process, a brand-new press box and grandstand will be built. Over the next few weeks construction crews will begin steel erection in the Commons, complete roofing on the Performing Arts wing as well start installing curtain wall in the Science Wing.

    March 2020
    Theater walls are up and more.

    Madison steel welder

    Madison has seen a lot of activity this month due to good weather. Walls are going up across the site with the walls of the new theater 80% complete and signifivcant steel framing in the science classroom wing is taking place.  On the south side of campus in the new Gym building concrete masonry walls for the wrestling room, weight room and food pantry are complete. As this area starts to take shape with door frames in place it’s possible to see yourself standing in front of what will be a future entryway to the future locker room.

    Elsewhere on the site footings have been started in the student health center, choir and band room.  In the classroom wing, a section that is being remodeled, roof framing and roughing in of the future class spaces is occurring.  Steel roofing is underway in the new media center.

    Madison Gym Wall

    January 2020
    Interior remodeling & seismic upgrades

    Madison Sheerwall

    Interior structural remodeling including the addition of seismic shearwalls is taking place at Madison this month. In the new gym building construction masonry unit (CMU)  blocks are being installed as the weight room, wrestling room, and locker rooms begin to take shape in the lower gym level. In the Administration and Science classroom wing the concrete slab has been poured. The orchestra pit CMU blocks continue to rise while the black box footings are installed.

    December 2019
    Demolition complete, interior remodeling begins

    If you drive by Madison High School you’ll notice many big changes. The original front entrance has been removed as have the original gym building, theatre and the cafeteria. Prior to their demolition, bricks, bleachers and the gym wood flooring were salvaged for re-use later on in the project.  

    Madison interior

    Hazardous material abatement has been completed and extensive remodeling is now underway.  The existing concrete structure is being modified and supplemented with new structural elements to bring the building up to current seismic standards.

    Madison Orchestra Pit framing

    In the new Performing Arts wing, the orchestra pit is in place.  The main building pad has also been poured, preparing the way for construction of the black box theater, band and choir classrooms.In the new gym, the foundations are underway and the masonry walls should start to rise in late January or early February.

    October 2019
    After a successful summer move into the Marshall Campus, Madison staff and students are into the swing of things in their new home for two years.  Artwork and posters came over from Madison to help the Marshall Campus feel like home. Prior to demo, the contractor has salvaged brick, bleachers and gym wood flooring for re-use on the project.

    Madison Theater Demolition

    At the project site, demolition and abatement are in going well. The first area demolished this summer was the administration wing, followed by the gym building and theatre. Interior abatement and architectural demo continues in the old cafeteria in prep for demolition. From the sidewalk on 82nd you can see a new pad going in.  This area will become the main office and the science beacon.

    Click here to view more pictures of the October work

    June 2019
    We started work in June and the contractor, Fortis, really hit the ground running! The main entrance/admin area has been abated and the interior demolition is nearly complete.  This wing will start to be demolished to the ground the week of August 19.  I wanted to let you know because that can be kind of fun to watch.  Feel free to stop by any time that week and view the demolition from Glenhaven Park.   Viewers c will need to stay outside of the construction fence and either be in Glenhaven Park or on the sidewalk along 82nd.

    Front of Madison demolished

    The gym, theater, and cafeteria demolitions will follow over the next 2-3 months, so there will be other opportunities to stop by for demolition viewing.  We’re working on a monthly update we can send out with photos and information on construction progress, so stay tuned.

    Click here to view more pictures of the summer work

    Madison Design Advisory Group (DAG)

    The goal of the Madison DAG is to develop comprehensive, equitable, integrated and visionary high school campus plans and schematic designs with authentic school community engagement.  The DAG will consist of a group of parent, teacher, student, and community stakeholder representatives who will be involved in the development of the design of the modernized Madison High School.

    Read the Madison Design Advisory Group (DAG) Charter | Español |Tiếng Việt | Русский | Soomaali

    Read the Design Advisory Group (DAG) Code of Conduct | Español |Tiếng Việt | Русский | Soomaali

    DAG Meeting #1 Presentation 12-11-17
    DAG #1 Mtg. Minutes 12-11-17
    DAG Meeting #2 Presentation 1-22-18
    DAG #2 Mtg. Minutes 1-22-18
    DAG #3 Mtg. Minutes 2-26-18
    DAG #4 Mtg. Minutes 3-19-18
    MHS DAG 4 Opsisi Theater Work 3-19-18
    DAG #5 Mtg. Minutes 5-14-18

    Madison Master Planning Committee (MPC)

    The Madison master planning committee (MPC) was a group of school and community stakeholder representatives who worked together to help provide feedback for the Madison master plans. MPC members synthesized community-wide input and shared the evolving details of the project to others in the community. While MPC members did not make decisions, their input was crucial in creating a design that the entire Madison community can be proud of. The committee began work in February of 2016 and completed their work in early 2017.

    Read The Madison Master Planning Committee Charter | Español |Tiếng Việt | Русский | Soomaaliga 

    The Madison master planning committee (MPC) roster | Español |Tiếng Việt

    MPC  #1 Presentation 2-16-16
    MPC #1 Mtg. Minutes 2-16-16
    Video of MPC Mtg.#1  2-16-16
    MPC#1  2016 Bond Lay of the Land Presentation
    MPC#1 Marcia Latta Outreach Presentation

    MPC #2 Presentation 3-7-16
    MPC #2 Mtg. Minutes 3-7-16
    MPC #2 Mtg. Boards/Words 3-7-16
    Video of MPC Mtg.#2 3-7-16

    MPC #3 Presentation 3-28-16
    MPC #3 Mtg. Minutes 3-28-16
    MPC #3 Mtg. Boards 3-28-16
    Video of MPC Mtg.#3 (3-28-16)

    MPC #4 Presentation 4-19-16
    MPC #4 Mtg. Minutes 4-19-16

    MPC #5 Presentation 5-9-16

    MPC # 6 Agenda 6-6-16

    MPC #6 Draft TOC

    MPC #6 Executive Summary Draft

    MPC #6 Executive Summary: SPHS

    Madison Master Plan Open House 5-23-16

    Madison Master Plan Open House 5-23-16

    MPC # 7 Meeting Minutes (11-15-16)
    MPC # 7 Presentation (11-15-16)

    MPC # 8 Presentation (12-12-16)
    MPC # 8 Meeting Minutes (12-12-16)

    Public Design Workshops

    During the master planning process one Public Design Workshop an open house and several community focused meetings took place providing the greater Madison community a voice in the design process.

Madison Project Images

Madison Construction 11-16-20

Madison Fly Through

Madison Timelapse Jan 2020

  • Madison Panoramas

    Madison 360 Panorama Render
    Click on the image to view a 360 degree render of the Madison HS redesign.
    View More Panoramas

Madison Groundbreaking

Madison Groundbreaking 5-18-19